200–700 m³/h Vacuum Pumps: Inlet Size and Power

200–700 m³/h, or 55.6–194 L/s, is the band most often compared on price: furnace roughing, coating line backing, chemical distillation, freeze drying and the main pump position in central vacuum systems. What goes wrong here is rarely the pump. Two details account for most of it: the inlet is sized one step too small and the piping eats half the pumping speed, or the motor is upsized “for safety” and the extra money buys no pump-down time. The figures below come from the published data for V0202, V0302, V300B and V630B.

1. Where the four models actually differ

ModelRated speed at 50 HzIn L/sUltimate (ballast closed)MotorInletWeight
V0202200 m³/h (240 at 60 Hz)55.60.1 mbar5.5 kWG2″ / G2″140 kg
V0302300 m³/h (360 at 60 Hz)83.30.5 mbar7.5 kWG2″ / G2″190 kg
DPL-V300B280 nominal / 240 actual66.7≤8×10⁻² mbar5.5 kWG2″ flange223 kg
DPL-V630B700 nominal / 640 actual177.8≤8×10⁻² mbar15 kWDN100 / DN160730 kg

Two differences are easy to miss. V0202 and V0302 are quoted with one rated figure, while V300B and V630B carry both nominal and actual values; nominal is for price comparison, actual is for pump-down time, and on V630B the gap is 8.6% (700 against 640). And V300B shares 5.5 kW with V0250 for only 10 m³/h more speed, yet reaches ≤8×10⁻² mbar against 0.5 mbar — that difference is the ballast valve and stage geometry, and it is why V300B is the right step when you need below 0.1 mbar without going two-stage. Full data: V0160–V0302 single-stage oil-sealed pumps, DPL-V300B, DPL-V630B.

2. Sizing the inlet: calculate the velocity first

The pump flange is a connection minimum, not a statement that the size can carry that flow. Velocity follows from continuity:

v = Q / A, with Q the actual pumping speed and A the pipe cross-section

For the four models, treating G2″ as DN50:

PipeV0202 200V0302 300V300B 240V630B 640 (m³/h)
DN50 (G2″)28.3 m/s42.4 m/s34.0 m/s90.5 m/s
DN8011.1 m/s16.6 m/s13.3 m/s35.4 m/s
DN1007.1 m/s10.6 m/s8.5 m/s22.6 m/s
DN1602.8 m/s4.1 m/s3.3 m/s8.8 m/s

Rough-vacuum main lines are normally kept within 15–20 m/s, with short straight runs tolerated up to about 25 m/s; the higher the velocity, the more of the pump’s speed is spent in the pipe. G2″ already reaches 28.3 m/s at 200 m³/h and 42.4 m/s at V0302’s 300 m³/h, which no amount of extra pipe length or bends can recover. Expand to DN80 or DN100 within half a metre of the pump flange and use the flange purely as an adapter. V630B is the other way round: 640 m³/h in DN100 is 22.6 m/s, acceptable only for a short straight run, so anything beyond three or four metres should go to DN160 at 8.8 m/s.

3. Speed conversion and effective pumping speed

Dividing m³/h by 3.6 gives L/s, and that single step fixes the basis for every later comparison: 240 m³/h is 66.7 L/s, 640 m³/h is 177.8 L/s. What the chamber sees is lower, because pump speed and piping conductance are in series:

1 / S_eff = 1 / S + 1 / C

A V300B at 240 m³/h behind a line with C = 240 m³/h gives S_eff = 120 m³/h, half the pump; bring the line to C = 480 m³/h and S_eff recovers to 160 m³/h. Pump-down time follows t = (V/S)·ln(P0/P1). A 5 m³ chamber from 1013 mbar to 1 mbar takes 5/240 × 6.92 h ≈ 0.144 h, or 8.7 minutes, at full speed, and 17.3 minutes at 120 m³/h. Same pump, same machine, 8.6 minutes of cycle time lost to piping alone.

The V630B comparison is sharper: a 10 m³ chamber at 640 m³/h is 10/640 × 6.92 h ≈ 0.108 h, or 6.5 minutes, twice the volume in less time. Note this holds for the roughing stage only; below 1 mbar the speed falls with pressure, so integrate the pump curve or use the pump-down calculator.

4. Power matching: specific power is flat across the band

Dividing motor power by actual speed gives V0202 36.4 m³/h per kW, V0302 40.0, V300B 43.6 and V630B 42.7. All four sit between 36 and 44, which says the band is one platform scaled by pump chamber size and specific energy does not jump with model. Upsizing only pays when speed is genuinely short; if the line is too small, a bigger pump just moves the waste from the pipe into the motor.

Voltages must match the site: V0202 and V0302 are three-phase 220/240 V and 380/415 V; V300B is 230 V / 400 V ±10% at 1500 r/min direct drive; V630B is 380–400 / 660–690 V or 415 V at 820 r/min. The 660–690 V option exists for high-voltage distribution, and changing it after the order costs far more than specifying it. A 15 kW direct-on-line start draws heavily, so check contactor and overload ratings against the motor nameplate rather than scaling up from 5.5 kW experience.

5. Where these models sit when a Roots stage is added

V0202 and V0302 typically back LC250 / LC500, V630B backs LC1200. The usual industry pairing is a 2:1 to 3:1 speed ratio, the backing pump at one third to one half of the Roots stage: too small and the bypass valve lifts constantly while the pump runs hot, too large and the extra cost buys no effective speed. Start order cannot be reversed — bring the system down to the few hundred to few thousand pascals the Roots stage accepts, then start it, and never bypass the differential interlock. See Roots pump units.

6. Three conditions that still apply

Gas ballast: V300B and V630B reach ≤8×10⁻² mbar closed and ≤0.7 mbar open; with moisture or solvent vapour, open it and judge the duty by pump-down time and oil condition rather than ultimate pressure. Add an inlet filter for dust. Oil charge is 8.5 / 11.5 L on V300B and 20 / 23 L on V630B.

Frequency: V0202 gives 240 m³/h at 60 Hz and V0302 360 m³/h, but some models are not suited to 60 Hz regions — confirm motor and speed configuration with the factory before export or a frequency change, and do not scale the 50 Hz sheet.

Frequently asked questions

Is a G2″ inlet enough for a 200–300 m³/h pump?
The flange is a connection minimum; expand the pipe. At 200 m³/h a V0202 reaches 28.3 m/s inside DN50 and a V0302 reaches 42.4 m/s at 300 m³/h, both above the 15–20 m/s used for rough-vacuum mains, so go to DN80 or DN100 within half a metre.
V300B is quoted at 280 m³/h nominal and 240 m³/h actual — which do I use?
Nominal for price comparison, actual for timing. The 280/240 gap is 14%; on a 5 m³ chamber from 1013 to 1 mbar, 240 m³/h gives about 8.7 minutes, and sizing on 280 underestimates the time by roughly 14%.
For 640 m³/h on a V630B, DN100 or DN160?
It depends on length. 640 m³/h in DN100 is 22.6 m/s, acceptable only for a short straight run of three to four metres; longer lines or several bends should use DN160 at 8.8 m/s. The pump offers both DN100 and DN160 inlets.
How much do specific power figures differ between a 5.5 kW V0202 and a 15 kW V630B?
Very little. On actual speed, V0202 gives 36.4 m³/h per kW and V630B 42.7, both on the same platform. The real difference comes from working pressure and ballast setting, not from the model.
Can a V630B back an LC1200 Roots unit?
Yes. The usual industry ratio is 2:1 to 3:1 between the Roots stage and its backing pump; with V630B at 640 m³/h, check the backing capacity against the unit's required speed, start the Roots stage only after roughing down to a few hundred to a few thousand pascals, and keep the differential interlock in service.

Need a model recommendation or a quote?

Tell us the required pumping speed, ultimate pressure, gas handled, dust and corrosion conditions, duty cycle and power supply; we will size the model for your process.

Contact us